By Zach Friend, County Supervisor 2nd District
- We have approval from Caltrans and FHWA to move forward with construction and are working out the final details
- We have recently completed procurement of the necessary right of way
- We have engaged with the utility companies that have facilities in the way of the construction and are working to address their needs
- We have selected a contractor to do the work and we are working with them on the plan to rebuild the slope and road
- We are working with the contractor on a schedule and traffic control plan.
•••