Resurfacing/Shoulder Widening at the Fishhook
Phase 1 will last about two months and will include the following closures:
The northbound Hwy. 1 loop ramp (Fishhook) has been reduced to one lane and is subject to full closures Monday through Friday from 8:00 p.m. until 5:30 a.m. Residents can expect considerable noise, depending on the roadwork being performed. Motorists may detour onto Pasatiempo Drive. Southbound Hwy. 17 will to be reduced to one lane Monday through Friday from 8 p.m. until 5:30 a.m.
Southbound Hwy. 17 will be reduced to one lane Monday through Friday from 10 p.m. until 5:30 a.m. The northbound Hwy. 1 ramp (Fishhook) will be subject to lane and full closures Monday through Friday from 8:00 p.m. until 5:30 a.m. Motorists may detour onto Pasatiempo Drive.
As currently planned, this week (Jan 25-29) includes tree removal, saw-cutting and excavation work. The following two weeks (Feb 1-5, Feb 8-12) will consist of working overnight on the barriers in front of all the bridge columns, which is all labor and will not be loud; day work will consist of underground work and electrical work. All work will depend on the weather and roadway surface conditions.
Motorists can expect delays not to exceed 15-20 minutes. This project, when completed in the spring, will create two dedicated lanes on northbound Hwy. 1 from the Fishhook. The contractor for this $1.2 million project is Granite Construction of Santa Clara, CA.
Caltrans reminds motorists to move over and slow down when driving through highway construction zones.
•••
For more information on this project and for traffic updates on other Caltrans projects in Santa Cruz County, residents can call the District 5 toll free number at 1-831-423-0396 or can visit our website at: http://www.dot.ca.gov/dist05/paffairs/release.htm#scr